Exeter City Council insourcing case study
The challenge
Exeter has six sites that were operated by Legacy Leisure along with a new £45m Passivhaus leisure centre that was due to open in 2021. The existing contract was coming to an end and a new procurement process started September 2019. Several bidders were shortlisted at SSQ stage: the incumbent was not one of them. After the first national lock down (March 2020), the council checked for continued interest from bidders but did not feel confident of any organization’s viability. The procurement was subsequently abandoned April 2020.
While the council used an open book approach to maintain the financial support package for the incumbent, retaining an operator on this arrangement indefinitely created financial risk. As the existing contract was coming to a natural end and having determined there was no longer appetite from other operators to take on risk or invest capital in the new centre fit out, the council decided an inhouse arrangement would be preferable. While recognizing the in-house service would be more costly by comparison to an external outsource, the council had more comfort in this option as they could budget for the calculated costs. An exit settlement was agreed with the incumbent a month prior to the contract end.
Due to the timing of the operator exit the council was left with responsibility for implementing COVID-19 safety procedures which meant the Exeter sites opened a month later than other centres across England, at the end of September 2020.
The solution
The insourcing process was supported by an external operational specialist three days a week, M&E consultants were engaged, there was internal HR support and external HR consultancy which cost circa £25K in total. Finance and legal support were secured inhouse.
Post transfer a restructure is taking place to align roles with the new service requirements. While the job evaluation process was unsettling staff are now happy and settled. The Sales and Marketing functions now come under the existing central marketing team that supports tourism in Exeter, while the finance team have absorbed the additional work.
The impact
The council started with a low membership base, as 60 per cent of members had left during the pandemic. A revenue budget of £1,542,130 was agreed to cover the cost of transfer and re-launch the service. An additional £270,000 was allocated to cover the cost recovery agreement with the incumbent operator. £330,000 of Capital budget was allocated to reopen the centres in a COVID-secure manner. The actual spend was £845k less than budgeted. This was down to several factors but principally the further lockdowns which reduced operating costs and provided access to the job retention scheme (JRS) payments.
The new £45m St Sidwells centre is due to open late 2021, with refurbishments at Riverside complete by Summer 2021 (pandemic delayed construction). It is anticipated these new developments will contribute towards reducing the new service subsidy with projections of break-even or possibly a surplus being made from 2023.
How is the new approach being sustained?
Post transfer the team is in a period of consolidation. Political and executive support remains positive. Leisure support services have been largely absorbed into the existing council departments. Monitoring is not yet in place.
The decision has been made not to outsource again in the future. When the disruption from transfer has settled the council may consider an LATC model to assist with managing the council partial exemption threshold.
Lessons learned
Ensure any council considering insourcing have operational knowledge leading the process or recruit this knowledge to support the transfer. Decisions need to be made quickly as the pace of transfer is fast, so ensure there is senior management and political support for decision making. Win the hearts and minds of transferring staff as they will reassure customers and support the process. The council made an active choice to bring the TUPE cohort inhouse and to offer staff council terms and conditions which was used to positively promote the process. Have confidence in the transferring staff – they know what needs to be done, so empower them in the process.
Contact: [email protected]
Hounslow insourcing to LATC
The case study outlines the council reversion of the leisure operation from Fusion Lifestyle to a newly established subsidiary Lampton Leisure (a LATC) of Lampton 360 (an existing LATC). It captures the challenges faced and how they were overcome, and includes valuable lessons learned from the London Borough of Hounslow council.
The challenge
The council felt that the service needed to be re-aligned to the long-term wellbeing objectives as set out in the corporate plan 2019-2024. Following an options appraisal, transfer into the council’s wholly owned company was deemed the best long-term solution to achieve these and other strategic objectives.
The solution
A mutually agreed early contract termination with Fusion Lifestyle, with reversion of the leisure facilities to council management via a newly established leisure LATC (Lampton Leisure); a subsidiary of the existing LATC (Lampton 360). The full transfer involved six leisure facilities (to the LATC), four public halls and a day centre (to direct management by the Council).
The Cabinet agreed the transfer on 8 September 2020, supported by an options appraisal. Once the decision was taken to transfer the leisure services to an LATC, the transfer was achieved within 8 weeks. Despite the additional complexities caused by new COVID-19 management regimes on re-opening, the transfer was achieved on 1 November 2020.
The impact
The options appraisal identified the best model as a transfer into the council wholly owned company to maximise the financial benefits and to bring added value to the council and its residents.
A mobilisation budget of £400,000 was approved; most of this budget was required for technology, asset repair costs, brand and associated set up costs. Support resource for leisure and project management costs was less than £100,000 which included leisure consultancy and project management costs between the LATC and the council.
The council’s objective was to deliver the services for no higher a cost than when outsourced.
How is the new approach being sustained?
An effective but light touch client function that focuses on the strategic outcomes and partnership working is in place.
Lessons learned
Specialist leisure and project management support was provided to the project board in the form of a PMO; alongside other specialist advice such as legal and transitional sales and marketing support.
The complexity, time and effort required to achieve the transfer must not be underestimated. The project had to deal with several challenges: demobilization, transfer, and mobilization of a new service in a new entity under a wholly owned company.
Governance structures and having clear strategic objectives were critical and were put in place from the project commencement, with project ownership and oversight by the executive director. Bringing the right team together across a range of functions to support delivery was important. The project team included leisure, communications, HR, legal, finance, procurement, corporate property, facilities management, digital and ICT and customer services.
Leisure expertise was essential throughout the project. This aided the loss of knowledge whilst the transfer was taking place and supported the new entity set up. Other areas of expertise that were brought in focused on sales and marketing functions, web and the use of multi-channel media.
Delegations were given through the cabinet to officers, to achieve the project objectives. This enabled quick actions and flexibility throughout the process.
ICT and GDPR issues were complex; system reconfiguration takes time which needed to be factored into the project planning.
Investment in the right support team was key to the success, this enabled officers to identify the risks ahead of time and design solutions.
Advisors need to work with the officers to apply local knowledge and to provide confidence in the navigation of multiple workstreams.
The emerging management team from the LATC / council need to be immersed in the process from the beginning, taking ownership of the shared objectives. The early transfer of a manager from the incumbent operator helped with logistical issues around the transfer.
All of the above contributed to the success of the transfer alongside the effective teamworking at all levels that enabled a quick delivery.
Contact: [email protected]
South Kesteven leisure insourcing
The challenge
The council have four centres that were operated by 1Life. Prior to the end of the contract term the council initiated an options appraisal. The preferred route at that time was to extend the current contract arrangement for 15 months to allow time for an external operator procurement process. COVID-19 happened and the council recognised that the market appetite had changed.
A risk assessment of the situation forced the council to reconsider the alternative options. One of these was the creation of a LATC which had not been selected originally as all risk would remain with the council and it was recognised there would be high set up costs. The decision for this went to cabinet August 2020 and secured approval.
The solution
Leisure consultants supported the original leisure options appraisal while legal counsel was received on the structure and creation of a new company, along with external tax advice on how to protect the council’s VAT exemption.
With only four months left on the existing contract the setup of Leisure SK Ltd (the LATC) and the transfer needed to take place by 31 Dec 2020. It was a significant project which was supported by the chief executive and leader and involved weekly meetings led by the council project team.
The staff transferred into the LATC with their terms and conditions intact to future proof a possible outsource again in the future.
The impact
£500,000 was allocated for the transfer and set up of the LATC £420,000 has been spent and the remainder rolled over to new financial year.
The service costs more than before the pandemic, but less than the period of national closures. There is a five-year trading plan in place projecting a small profit from year two.
How is the new approach being sustained
The feedback on the new service so far from customers and the council’s Scrutiny Committees has been good. Karen heads up the monitoring regime which is a two-sided process with a balanced performance scorecard.
Lessons learned
Timing can trip you up, transfer arrangements differ between tasks and some need more time than you have, so you have to adapt; for instance, the transfer of data and set up of the leisure management software with Gladstone took four months. The bank account took some time to be set up which delayed the setting up of suppliers. Transferring staff were consulted with very early on, to inform them of what was happening and to gain confidence and support for the transfer. Employee representatives were established, and regular zoom calls took place on any key staffing issues as they arose.
Contact: [email protected]